Cold Storage Pioneer in Industrial Design
Written by: TunelGroup Engineering Content Team
Technical review: Hamza ILIMAN — Project Coordinator
Last updated: August 28, 2026
Content type: Technical engineering guide
Cold Room Load Calculation determines the required refrigeration capacity by adding transmission, product cooling, freezing, respiration, air infiltration, internal, evaporator fan, defrost and auxiliary heat loads. Equipment must then be selected at the actual design evaporating and condensing conditions. Room volume or compressor horsepower alone is not a reliable sizing method. For a −18°C freezer room operating in a +35°C ambient environment, TunelGroup generally recommends a minimum 100 mm PUR/PIR insulated panel as a preliminary starting point; final panel thickness and refrigeration capacity must be confirmed from the room dimensions, product throughput, product entry temperature, pull-down time, door activity, operating hours and local energy and safety requirements.
Engineering notice: This guide explains the calculation method and includes an illustrative example. It is not a final equipment selection, construction design or substitute for a project-specific calculation by a qualified refrigeration professional.
A cold room load calculation determines how much heat the refrigeration system must remove to maintain the required room and product temperatures under defined operating conditions.
The basic calculation structure is:
Total refrigeration load = transmission load + product sensible load + product latent load + respiration load + infiltration load + internal loads + fan load + defrost and auxiliary loads
The result is normally expressed in:
Kilowatts of refrigeration: kW
British thermal units per hour: Btu/h
Tons of refrigeration: TR
Useful conversions are:
| Unit | Equivalent |
|---|---|
| 1 kW | Approximately 3,412 Btu/h |
| 1 TR | Approximately 3.517 kW |
| 1 TR | 12,000 Btu/h |
The final equipment must be selected from verified manufacturer performance data at the project duty point. A unit advertised as “20 kW” may deliver a different capacity when the evaporating temperature, condensing temperature, refrigerant, superheat, subcooling or ambient condition changes.
The 2026 ASHRAE Handbook—Refrigeration includes dedicated guidance on refrigerated-facility design and loads, thermal properties of foods, cooling and freezing times, storage and industrial refrigeration. The calculation should also be checked against the standards and regulations applicable in the project country.
Two cold rooms with the same volume can require very different refrigeration capacities.
For example, a 300 m³ room used only to hold already-frozen products may have a much lower load than a 300 m³ room receiving several tonnes of warm product every day. Door traffic, ambient humidity, panel performance, pull-down time and evaporator fan power can create larger differences than room volume itself.
| Same room volume, different condition | Effect on refrigeration load |
| Product enters at storage temperature | Low product load |
| Product enters warm or unfrozen | High sensible and possibly latent load |
| Door opens twice per day | Lower infiltration load |
| Door remains active during loading | Higher sensible and moisture load |
| Room is inside a conditioned building | Lower transmission load |
| Room is exposed to hot outdoor conditions | Higher transmission and condensing load |
| Thick, well-sealed panels | Lower envelope load |
| Damaged joints or unsealed penetrations | Higher heat and moisture infiltration |
TunelGroup’s existing cooling capacity calculator can provide a preliminary estimate. A commercial project should proceed with a detailed load calculation using actual operating data.
An accurate calculation begins with complete inputs. Unknown values should be marked as assumptions and approved before equipment selection.
| Required input | Unit or description | Why it matters |
| Internal room dimensions | m | Defines volume and internal layout |
| External envelope dimensions | m | Defines transmission surface area |
| Wall, ceiling and floor area | m² | Used in the transmission calculation |
| Panel thickness | mm | Influences thermal transmittance |
| Declared panel U-value | W/m²·K | Required for heat-transfer calculation |
| Floor construction | Layers and U-value | Critical for freezers and ground interfaces |
| Door dimensions and quantity | mm and units | Influences transmission and infiltration |
| Thermal bridges | Junction details | Adds heat beyond clear-panel performance |
| Solar and weather exposure | Orientation and location | Affects exposed surfaces and design ambient |
| Required input | Unit or description | Why it matters |
| Product type | Meat, fruit, vegetables, dairy, etc. | Determines thermal and respiration properties |
| Maximum stored quantity | kg or tonnes | Defines storage capacity, not daily load by itself |
| Daily product intake | kg/day | Major product-load input |
| Product entry temperature | °C | Determines heat that must be removed |
| Target product temperature | °C | Defines the cooling endpoint |
| Freezing point | °C | Required if the product crosses its freezing range |
| Specific heat above freezing | kJ/kg·K | Used before freezing |
| Latent heat of freezing | kJ/kg | Used during phase change |
| Specific heat below freezing | kJ/kg·K | Used after freezing |
| Required pull-down time | hours | Converts product energy into required capacity |
| Packaging and pallet pattern | Type and layout | Affects airflow and cooling time |
| Required input | Unit or description | Why it matters |
| Outdoor design temperature | °C dry bulb | Sets transmission and condensing conditions |
| Outdoor humidity | % RH or wet bulb | Required for infiltration moisture load |
| Adjacent-space temperatures | °C | Each surface may have a different temperature difference |
| Door-opening duration | min/hour or min/day | Required for infiltration calculation |
| Door-opening frequency | openings/hour or day | Defines traffic intensity |
| Traffic protection | Air curtain, strip curtain, vestibule | Reduces air exchange when correctly applied |
| People inside | Persons and hours/day | Adds sensible and latent heat |
| Lighting | W and hours/day | Becomes an internal heat load |
| Forklifts and machinery | kW and operating hours | Can be a major internal load |
| Evaporator fans | W and operating hours | Fan energy normally enters the refrigerated space |
| Defrost method | Electric, hot gas, off-cycle | Determines defrost heat input |
| Compressor availability | Operating hours/day | Influences required installed capacity |
Transmission load is the heat entering through the walls, ceiling, floor, doors and other envelope components.
For each surface:
Qₜ = U × A × ΔT
Where:
| Symbol | Meaning | Unit |
| Qₜ | Transmission heat gain | W |
| U | Overall thermal transmittance | W/m²·K |
| A | Surface area | m² |
| ΔT | Temperature difference across that surface | K |
Calculate walls, ceiling, floor and doors separately when their U-values or adjacent temperatures differ.
For 286 m² of envelope area, a design U-value of 0.23 W/m²·K and a 53 K temperature difference:
Qₜ = 0.23 × 286 × 53 = 3,487 W ≈ 3.49 kW
This clear-panel result does not automatically include:
Panel joints
Corners
Floor-wall connections
Door frames
Structural steel penetrations
Pipe and cable penetrations
Damaged vapor seals
Thermal bridges should be calculated from known details or covered with a documented project allowance. A percentage allowance should not be used to hide incomplete envelope information.
Product sensible load is the heat removed while changing product temperature without a phase change.
Qₚ = m × cₚ × (Tᵢ − T𝒻) ÷ (t × 3,600)
Where:
| Symbol | Meaning | Unit |
| Qₚ | Average product cooling load | kW |
| m | Product mass entering during the period | kg |
| cₚ | Product specific heat | kJ/kg·K |
| Tᵢ | Product entry temperature | °C |
| T𝒻 | Final product temperature | °C |
| t | Required cooling time | hours |
If 8,000 kg of frozen meat enters at −10°C and must reach −18°C within 20 hours, using an illustrative below-freezing specific heat of 1.7 kJ/kg·K:
Qₚ = 8,000 × 1.7 × 8 ÷ (20 × 3,600) = 1.51 kW
The specific heat must be taken from a reliable product-property source for the actual food composition and temperature range. The 1.7 kJ/kg·K value above is an example assumption, not a universal meat value.
If the product enters above its freezing point and leaves below it, the product load has three stages:
Sensible cooling above the initial freezing point
Latent heat removal during ice formation
Sensible cooling below the freezing range
The simplified calculation is:
Qfreeze = m × [cₚ₁(Tᵢ − Tfreeze) + Lfreeze + cₚ₂(Tfreeze − T𝒻)] ÷ (t × 3,600)
Where Lfreeze is the product’s effective latent heat of freezing in kJ/kg.
Freezing load can dominate the project. A storage freezer designed to hold frozen cartons should not automatically be used as a blast freezer for warm or unfrozen product. Blast freezing requires a separate analysis of product geometry, packaging, air velocity, freezing time, evaporating temperature and product-quality targets.
Fresh fruits, vegetables and other living products continue to respire after harvest and release heat.
Qᵣ = mstored × qresp
Where:
| Symbol | Meaning | Unit |
| Qᵣ | Respiration load | W |
| mstored | Mass of stored product | kg |
| qresp | Respiration heat rate at storage temperature | W/kg |
Respiration rate changes significantly with product type, cultivar, maturity and temperature. Use product-specific post-harvest data at the intended storage temperature.
Respiration load is normally not applied to frozen meat. It can be important in high-capacity fruit, vegetable and controlled-atmosphere stores.
When a cold-room door opens, warm outdoor air enters and cold dense air leaves. The refrigeration system must remove both the sensible heat and the moisture-related latent load.
An enthalpy-based method is:
Qᵢ = ṁair × (hout − hin)
Where:
| Symbol | Meaning | Unit |
| Qᵢ | Infiltration load | kW |
| ṁair | Infiltrating air mass flow | kg/s |
| hout | Outdoor-air enthalpy | kJ/kg dry air |
| hin | Cold-room-air enthalpy | kJ/kg dry air |
Air mass flow may be estimated from a validated air-change method or calculated from door dimensions, opening time, temperature difference, pressure effects and traffic-protection efficiency.
For freezer rooms, infiltrating moisture can freeze on the evaporator. This increases both the refrigeration load and the required defrost frequency. Outdoor dry-bulb temperature alone is therefore insufficient; outdoor humidity or wet-bulb condition is also required.
Large doors
Long door-open periods
High traffic
Damaged gaskets
Missing strip curtains or vestibules
Pressure imbalance
Warm and humid outdoor conditions
Loading docks exposed directly to weather
Most electrical power used inside the refrigerated space eventually becomes heat that must be removed.
Qlights = Installed lighting power × simultaneous-use factor
Use the actual fixture input power, including drivers. Timers, occupancy sensors and efficient LED lighting can reduce daily energy use.
Occupant heat depends on activity level, clothing and room temperature. Use an appropriate sensible and latent heat value and the maximum realistic occupancy during loading or inspection.
Include the portion of equipment power released inside the room. Electric forklift motors, battery losses, conveyors, heaters and processing equipment may create significant intermittent loads.
Freezer-door frame heaters, pressure-balance valve heaters, drain heaters and floor-heating systems must be included according to their power and duty cycle. Floor-heating energy is normally designed to protect the subfloor from freezing and must be coordinated with the floor heat-transfer calculation.
Evaporator fan power is normally released inside the refrigerated space.
Qfans = Σ fan input power × operating factor
Do not use only the fan motor’s nominal mechanical output. Use electrical input power or verified equipment data where available.
Variable-speed EC fans can reduce fan heat and electrical consumption during stable storage. However, airflow must remain sufficient for:
Product cooling
Uniform room temperature
Coil heat transfer
Moisture control
Required air throw
Open return-air paths
TunelGroup’s ceiling-type evaporators can be selected according to calculated capacity, temperature difference, air volume, fan pressure, fin spacing and defrost requirements. Eurovent’s Heat Exchanger certification programme covers declared performance for refrigeration air coolers and other heat exchangers; certification or rated-product data helps verify equipment performance but does not replace the project heat-load calculation.
Electric defrost heaters can have a high nameplate power, but not all heater energy necessarily enters the room over the complete day. The calculation should consider:
Heater power
Number of defrost cycles per day
Defrost duration
Heat absorbed by the coil and ice
Heat reaching room air and products
Fan delay and drip time
Door heaters and drain heaters
For an average daily method:
Qdefrost,avg = Energy entering refrigerated space per day ÷ 24 hours
Hot-gas, electric and off-cycle defrost systems have different load and control characteristics. The chosen method should match room temperature, frost load, coil design and operating schedule.
Adding the load components gives the room’s calculated heat load. Equipment selection still requires several checks.
If the calculated daily heat gain is expressed as kWh/day and the compressor is expected to have only a limited operating window:
Required average capacity = Total daily heat load ÷ Available compressor operating hours
Do not divide by 24 hours when the design intentionally reserves time for defrost, pull-down recovery, maintenance or demand management.
The compressor, condensing unit and evaporator must be checked at:
Refrigerant
Required room temperature
Design evaporating temperature
Design condensing temperature or outdoor ambient
Suction-gas superheat
Liquid subcooling
Voltage and frequency
Compressor speed, where variable
Fouling and airflow conditions
AHRI lists AHRI 420/421 for forced-circulation unit coolers and AHRI 1250/1251 for walk-in cooler and freezer performance ratings. These rating methods support comparable equipment data; they do not calculate the building’s project-specific refrigeration load.
A modest, documented allowance may be applied for calculation uncertainty, future operating variation or equipment degradation. It should be visible as a separate line.
Avoid hiding missing data inside an arbitrary oversizing factor. Excessive capacity can increase cost, shorten compressor cycles, complicate humidity control and reduce part-load efficiency.
One room may use a monoblock, hermetic split or semi-hermetic system, while a large facility may require multiple compressors or a central system. The decision should consider:
Critical product value
Required redundancy
Part-load efficiency
Maintenance access
Future expansion
Refrigerant-charge strategy
Local refrigerant rules
Backup power
Noise and heat-rejection limits
TunelGroup’s refrigeration units include different system configurations that can be matched to the verified project load and operating conditions.
Panel thickness is not determined from room temperature alone. The declared U-value, insulation core, joint design, vapor sealing, structural requirements, fire classification, ambient condition and local energy code must all be checked.
The following table is TunelGroup preliminary design guidance, not a universal standard or final specification:
| Application | Typical room condition | Preliminary PUR/PIR starting point | Engineering note |
| Mild chilled room | +8°C to +15°C | 60–80 mm | Confirm humidity, exposure and local code |
| Commercial chiller | 0°C to +8°C | 80 mm | Increase where ambient or energy targets require |
| Frozen storage | Approximately −18°C at up to +35°C ambient | Minimum 100 mm | Confirm floor insulation, vapor barrier and door design |
| Low-temperature freezer | Approximately −25°C at up to +35°C ambient | 120 mm | Check frost protection and thermal bridges |
| Blast freezer | Approximately −35°C to −40°C | 150 mm or engineered solution | Product-freezing load and pull-down usually dominate |
For a −18°C freezer operating in +35°C ambient conditions, a minimum 100 mm PUR/PIR panel is a practical preliminary recommendation. It is not permission to skip the U-value and transmission calculation.
TunelGroup’s cold room wall panels can be configured according to project temperature, surface material, hygiene, structural and insulation requirements.
The following example demonstrates the method. All unverified values are clearly marked as assumptions.
| Input | Example value | Status |
| Internal dimensions | 10 × 8 × 3.5 m | Assumption |
| Internal volume | 280 m³ | Calculated |
| Approximate envelope area | 286 m² | Calculated |
| Room temperature | −18°C | Design target |
| Outdoor design temperature | +35°C | Assumption |
| Outdoor relative humidity | 40% RH | Assumption |
| Cold-room relative humidity | 90% RH | Illustrative psychrometric assumption |
| Temperature difference | 53 K | Calculated |
| Panel design U-value | 0.23 W/m²·K | Assumption; verify supplier declaration |
| Daily frozen-meat intake | 8,000 kg | Assumption |
| Product entry temperature | −10°C | Assumption |
| Target product temperature | −18°C | Design target |
| Product cooling time | 20 hours | Assumption |
| Below-freezing product specific heat | 1.7 kJ/kg·K | Illustrative assumption |
| Effective infiltration | Equivalent 0.20 ACH | Illustrative assumption; calculate from door use |
| Evaporator fans | 4 × 0.35 kW | Assumption |
| Load component | Example calculation basis | Result |
| Clear-envelope transmission | 0.23 × 286 × 53 | 3.49 kW |
| Thermal-bridge allowance | 10% of clear-envelope load | 0.35 kW |
| Frozen-product sensible load | 8,000 × 1.7 × 8 ÷ (20 × 3,600) | 1.51 kW |
| Infiltration | Approx. 0.0178 kg/s × 88 kJ/kg enthalpy difference | 1.56 kW |
| Evaporator fan heat | 4 × 0.35 | 1.40 kW |
| Lighting | Assumed coincident input | 0.40 kW |
| People | Assumed loading-period heat | 0.50 kW |
| Defrost and auxiliary heat | Assumed equivalent design contribution | 0.60 kW |
| Calculated design load | Sum of listed components | 9.81 kW |
| Design allowance | 10%, shown separately | 0.98 kW |
| Preliminary selection benchmark | Before manufacturer duty-point verification | 10.79 kW |
The result does not mean that any nominal 11 kW refrigeration unit is suitable. Final selection must verify:
Actual door-opening and humidity data
Product properties and real daily intake
Compressor operating hours
Required pull-down and recovery time
Refrigerant and local regulatory limits
Capacity at the selected evaporating and condensing temperatures
Evaporator TD, air volume, air throw and defrost
Condenser capacity at the outdoor design condition
Pipe sizing and pressure drop
Part-load operation and redundancy
If the meat enters unfrozen or above its freezing range, latent heat must be added and the required capacity may rise substantially.
| Recommended | Not recommended |
| Calculate each load component separately | Select equipment only from room volume |
| Use maximum realistic daily product intake | Use total stored tonnage as daily throughput |
| Use actual product entry temperature | Assume every product enters at room temperature |
| Define the required pull-down time | Ignore how quickly the product must cool |
| Use design outdoor dry-bulb and humidity data | Use only annual average temperature |
| Calculate door infiltration from real usage | Apply one unexplained door factor to every project |
| Include evaporator fan and defrost heat | Ignore electrical loads inside the room |
| Use declared panel U-values and connection details | Choose panel thickness by habit alone |
| Verify equipment at actual SST/SCT conditions | Use nominal catalogue capacity at unrelated conditions |
| Show safety or design allowances separately | Hide missing data inside a large oversizing factor |
| Check part-load performance and redundancy | Install one large compressor without operational analysis |
| Record all assumptions and revision dates | Publish a calculation with no traceable inputs |
Compressor horsepower is not refrigeration capacity. Two compressors with the same motor class can deliver different capacities at different operating conditions.
Holding an already-cold product and cooling a warm incoming product are different duties. Daily intake and cooling time must be stated.
When product crosses its freezing range, latent heat may become the largest load component.
A ceiling below a hot roof, a wall beside an air-conditioned room and a freezer floor above soil have different boundary conditions.
Warm humid air adds both heat and frost. A dry-bulb-only estimate can understate evaporator and defrost requirements.
Evaporator fans operate inside the cold room. Their electrical input should be included with the appropriate operating factor.
Uncontrolled oversizing may increase first cost and create short cycling or poor humidity performance. The allowance should be justified and visible.
A calculation is complete only when the selected system is checked against the real installation and operating plan.
Before approval, verify:
Room and envelope dimensions
Panel U-values and thicknesses
Floor and vapor-barrier construction
Door size, quantity and traffic schedule
Product type, intake, entry temperature and pull-down time
Outdoor design temperature and humidity
Compressor and condensing-unit capacity at the duty point
Evaporator capacity, TD, airflow and defrost
Condenser performance at design ambient
Refrigerant safety and charge limitations
Electrical voltage and frequency
Controls, alarms and sensor locations
Drainage and freezer floor protection
Maintenance clearances
Backup and redundancy strategy
After installation, commissioning should verify:
Sensor calibration
Room pull-down trend
Product-temperature response where applicable
Suction and discharge conditions
Superheat and subcooling
Airflow and return-air paths
Defrost termination and drainage
Door sealing
Alarm operation
Energy and operating trends
ASHRAE provides a Refrigeration Commissioning Guide covering refrigerated-facility design, heat-load calculation, system design, controls, energy modelling and commissioning.
The latest edition adopted by the project jurisdiction should always be confirmed. Standards have different purposes: a safety standard is not a heat-load formula, and a performance-rating standard is not a complete project design.
| Reference | Relevance to the project |
| 2026 ASHRAE Handbook—Refrigeration | Refrigerated-facility design and loads, food thermal properties, cooling, freezing, storage and low-temperature systems |
| ISO 5149-1:2014 and amendments | Refrigerating-system safety, environmental requirements, classification and selection criteria; confirm the latest adopted revision |
| ASHRAE Standard 34-2024 overview | Refrigerant designations, safety classifications and concentration limits |
| AHRI refrigeration standards | Performance rating references for compressors, unit coolers and walk-in systems |
| Eurovent Heat Exchanger certification | Third-party performance certification for refrigeration air coolers and heat exchangers |
| 10 CFR Part 431, Subpart R | U.S. energy-conservation and test requirements for covered walk-in coolers and freezers |
| USDA FSIS beef freezing guidance | U.S. food-safety reference noting 0°F, approximately −17.7°C, for frozen beef storage |
Project teams must also check local building, fire, electrical, pressure-equipment, food-safety, refrigerant and environmental regulations.
This technical page should use original TunelGroup photographs, not generic stock images presented as project evidence.
| Recommended real image | What it should prove | Suggested alt text |
| Installed wall and ceiling panels | Real panel joints and envelope quality | TunelGroup insulated cold room panels installed in a commercial freezer |
| Panel label or measured section | Actual panel specification | 100 mm PUR PIR cold room panel section used for freezer insulation |
| Refrigeration unit with nameplate | Selected compressor and equipment identity | TunelGroup refrigeration unit selected from a cold room load calculation |
| Ceiling evaporator installation | Air distribution and installation clearance | Ceiling evaporators installed for uniform airflow in an industrial cold room |
| Heated freezer door | Door size, gasket and frame-heater detail | Heated sliding freezer door in a minus 18 degree cold room |
| Digital control panel | Temperature, defrost and alarm control | Digital cold room control panel monitoring refrigeration operation |
| Commissioning screen or trend | Measured operating evidence | Cold room commissioning temperature trend recorded after system startup |
Publication rule: Remove customer names, prices, serial numbers and confidential documents unless publication permission has been obtained. Captions must distinguish completed-project photographs from proposal renders or illustrative diagrams.
TunelGroup develops project-specific cold room solutions using room geometry, product data, operating conditions and local design requirements.
Depending on the project, the engineering scope may include:
Refrigeration load calculation
Panel thickness and envelope selection
Cold room door specification
Compressor and condensing-unit selection
Evaporator selection and airflow planning
Refrigerant and system-architecture evaluation
Pipe and electrical input definition
Digital controls and alarm strategy
Installation and commissioning support
TunelGroup can combine cold room panels, refrigeration units, evaporators and digital control panels as one coordinated project package.
For an engineering evaluation, provide:
Project country and city
Room dimensions
Required room temperature
Product type
Total storage capacity
Maximum daily product intake
Product entry and target temperatures
Required pull-down time
Packaging and pallet layout
Door dimensions and usage schedule
Outdoor design temperature and humidity
Electrical supply
Installation and commissioning scope
Add transmission, product, freezing, respiration, infiltration, internal, fan, defrost and auxiliary loads. Then verify equipment capacity at the actual evaporating and condensing conditions and account for available compressor operating hours.
Room volume can support a preliminary estimate, but it is not sufficient for final equipment selection. Product throughput, entry temperature, door use, insulation, ambient humidity and pull-down time may change the load substantially.
For a −18°C freezer operating in an ambient temperature up to approximately +35°C, TunelGroup generally uses 100 mm PUR/PIR as a minimum preliminary starting point. The final thickness must be confirmed from the U-value, room exposure, floor construction, energy requirements and local code.
No. Horsepower describes a motor or compressor class, while refrigeration capacity depends on refrigerant and operating conditions. Use verified capacity data at the project duty point.
Yes, whenever incoming product is warmer than its target temperature. The room air may already be cold while the product still introduces a large heat load.
Latent heat must be included when the product crosses its freezing range or when moisture condenses or freezes because of air infiltration or process conditions.
Yes. Fan electrical input normally becomes heat inside the refrigerated space and should be included with the correct operating factor.
There is no universal percentage for every project. Use a modest, documented design allowance based on the quality of the input data, operating variation, future needs and redundancy strategy. Do not use a large safety factor to conceal missing information.
An enthalpy-based method multiplies infiltrating air mass flow by the difference between outdoor- and indoor-air enthalpy. Door size, opening duration, temperature, humidity and traffic protection must be considered.
No. Equipment must be selected at the design evaporating and condensing temperatures, which differ from room and outdoor temperatures because heat exchangers require temperature differences.
A reliable Cold Room Load Calculation must go beyond room volume. The correct refrigeration capacity comes from transparent calculation of envelope transmission, product cooling and freezing, respiration, door infiltration, people, lighting, machinery, evaporator fans, defrost and auxiliary heating.
The final system should be selected only after its capacity is verified at the actual refrigerant and duty conditions. Assumptions, safety allowances and excluded information should be shown clearly so the calculation can be reviewed, updated and cited.
TunelGroup uses this project-specific approach to coordinate insulation, refrigeration equipment, evaporators, doors and controls for commercial and industrial cold rooms.
Our Mega Structure Design and Manufacturing Efficiency is at the Top Level with Knowledge, Experience and Effective Engineering